Project Progress

House Mountain

Progress Information

Address: 9601 Hogskin Road 37901
Architect: T.B.D.
Construction Manager: T.B.D.
Budget: $ 253,491
Construction Start Date: T.B.D.
Estimated Completion Date: T.B.D.

Description:

The scope of work includes the construction of a new parking lot and restroom / shelter facility. The RFP for design services will go out in mid May was advertised June 5 . The State requested that the due date for proposals be postponed until July 18. Architect evaluations are scheduled for August 1.

House Mountain Quarterly Report

  • Groundbreaking ceremony held October 24, 2005
  • Contract for Architectural/Engineering services executed on October 27, 2005 with Thomas Caldwell Architects
  • Topographic survey performed by R A Bailey Co. November 6, 2005
  • Initial programming meeting held on November 28, 2005
  • Preliminary Design review meeting held December 12, 2005
  • Schematic Design and cost estimate review meeting held January 5, 2005
  • Schematic Design submitted to State Architect for review on January 18, 2005
  • State approval of Schematic Design received on January 24, 2006 Construction Document review meeting held February 5, 2006
  • Final Construction Document review meeting held February 24, 2006
  • Request for Proposals for a Contractor will be advertised on Sunday, March 5, 2006
    • The pre-bid meeting is scheduled for Tuesday, March 14, 2006
    • The proposals are due on Tuesday, March 28, 2006
  • Design includes reconfiguration of the parking area, construction of a restroom facility, picnic pavilion, improved lighting and the addition of sidewalks to make restroom and shelter accessible


Upcoming Events at this Project Site

T.B.A.