Halls Community Park
Progress Information
Architect: Michael Brady Inc.
Construction Manager: Evans Contracting
Budget: $
1,000,000
Construction Start Date: July 2005
Estimated Completion Date: June 2006
Description:
The project involves the construction of new ball fields, modifications to existing fields, and upgrades to parking and existing facilities. The GMP is being finalized. Grading work started in July. Substantial completion is scheduled for December 2005, with only the sprigging of the football field remaining in the Spring. |
Upcoming Events at this Project Site
T.B.A.
Photos/Renderings