Halls Senior Center
Progress Information
Address: Off Crippen Road,
Knoxville, TN 37938
Architect: Michael Brady Inc.
Construction Manager: Evans Constracting
Budget: $1,258,000
Construction Start Date: June 2005
Estimated Completion Date: January 2006
Description:
This project includes a n approximate 9,800 SF new facility for a new senior center . The project involves the construction of a new senior center. Design development is complete. Construction will begin by December 2004 Construction Documents are complete. Grading is underway complete . Foundations s are complete package is being bid . A picnic is planned for was held June 9 at the site. The GMP is being finalized pending funding.